Participant Handbookالعربية Download PDF
NextEmTech

Project Management for Startups

From Vision to Execution · Participant Handbook
EPM-JO Bootcamp · PMI Jordan Chapter × INJAZ mySTARTUP
Wednesday 28 October 2026 · 13:00–16:30
Trainer: Deeb Haddad, PMP
TimeSessionYour output
13:00–13:251. Why startups fail on execution; PM for startupsStage and approach
13:25–13:502. From vision to execution planOne-page execution plan (A3)
13:50–14:153. Assumption testing3 riskiest assumptions + tests
14:15–14:45Lunch break—
14:45–15:104. MVP scope and resourcesTop-5 MVP backlog
15:10–15:405. Risk and founder accountabilityRisk register + decision rights (A3)
15:40–16:006. Agile operating rhythmWeekly rhythm
16:00–16:157. PMI tools and learning pathways (CAPM)Personal learning pathway
16:15–16:308. Closing30-day commitment card

Cases marked “composite” are realistic teaching examples, not real companies; their figures are illustrative. Real cases are summarised from public sources. This workshop is not PMP or CAPM exam preparation and is not legal advice.

Session 1 · 13:00–13:25

Why startups fail on execution

Execution failure can be diagnosed. Every failure pattern shows early symptoms. Project management spots them early (discovery) and acts on them (resolution).

The Execution Failure Diagnostic

#PatternEarly symptomDiscover it withResolve it with
F1Building the wrong thingFeatures shipped, few paying usersNeeds assessment; stakeholder analysis; interviewsProblem statement; acceptance criteria; test before building
F2Cash runs out before evidenceNobody knows the monthly burn or runwayCost baseline; planned vs. actual spendSpend per proven milestone; runway = cash ÷ net monthly burn
F3Everything urgent, nothing finishedMany tasks in progress, few doneVisible backlog; Kanban boardMoSCoW; work-in-progress limit; one sprint goal
F4Nobody owns it / founder deadlockTasks fall between foundersRACI matrixOne accountable owner; decision rights; escalation rule
F5Surprises that block launchLaunch stopped by a legal, tax, data or supplier issueRisk identification; assumption and constraint logRisk register with owner and response

Global data: CB Insights (2021, 111 startup post-mortems) — founders cited running out of cash (38%) and no market need (35%) as top reasons. Not Jordan statistics.

Three types of work

  • Project: temporary, unique result (MVP v1, company registration, a pilot).
  • Operation: ongoing and repeated (support, accounting, deliveries).
  • Experiment: a small test to learn, then decide.

Approach by stage

  • Idea / validation: experiments.
  • MVP: agile sprints inside fixed milestones.
  • Operating: hybrid — fixed: legal, tax, contracts, funder milestones; flexible: features.
Jordan example (composite): an Amman invoicing app spends 4 months polishing screens and leaves the JoFotara e-invoicing integration for “later”; pilot shops cannot invoice compliantly. Fix: treat JoFotara as a fixed, predictive milestone and keep the screens agile.
Why CAPM-level practice helps: the four CAPM domains — business analysis, fundamentals, predictive and agile methods — give a team the shared language and basic tools to find and fix these five patterns.
Session 2 · 13:25–13:50

From vision to execution plan

A plan is a chain: vision → outcome → milestones → owners → resources → KPIs. If one link is missing, execution breaks there.
LinkQuestionQuality test
VisionWhy do we exist?One sentence, customer-centred, 3 years
90-day outcomeWhat must change for the customer or business?A result, not an activity
Key resultsHow will we know?2–3 numbers with target and date
MilestonesWhat proven steps lead there?Dated; “done” = evidence
OwnersWho is accountable?One name, never “the team”
ResourcesWhat do we have and lack?People, cash, runway in months, gaps
KPIsWhat do we watch weekly?2 leading + 1 lagging; no vanity metrics

Rules that matter

  • Output ≠ outcome. “Launch the app” is an output; “20 paying shops” is an outcome.
  • SMART objectives; OKR: one objective, 2–3 key results.
  • If a key result cannot be counted on a date, it is not a key result.
  • Rolling wave planning: detail the next 90 days; re-plan monthly.

Example (composite, Case A)

  • Vision: every small shop in Jordan issues a compliant invoice in under a minute.
  • KRs by day 90: 20 paying shops; ≥ 95% invoices accepted by JoFotara first time; ≥ 70% of shops active 4+ days a week.
  • Runway: JD 18,000 ÷ JD 3,000 burn = 6 months.

Output → outcome across industries (illustrative)

IndustryWeak outputStrong outcome
Health techLaunch the booking app3 clinics get ≥ 30% of bookings via the app by day 90
E-commerceLaunch our website≥ 40% of orders prepaid; returns ≤ 8%
Edtech (Tawjihi)Record 100 videos200 weekly active students; ≥ 60% of parents renew
AI chatbotTrain the chatbotResolves ≥ 60% of chats without a human; satisfaction ≥ 4/5
Agri-techBuild a marketplace10 restaurants reorder weekly from 15 farms
Session 3 · 13:50–14:15

Assumption testing

Every key result is a hypothesis. Test the riskiest assumption cheapest and fastest. What customers say is weak evidence; what they do is stronger; what they pay is strongest.

Validation cycle

Diagnose → Hypothesize → Experiment → Measure → Decide

Four assumption types

  • Desirability: do they want it?
  • Viability: will they pay enough?
  • Feasibility: can we build and deliver it?
  • Compliance: are we allowed (JoFotara, PDPL, licences)?

Riskiest = high importance, low evidence.

Experiment ladder (cheapest first)

  1. Problem interviews (10–15)
  2. Landing page or demo video with sign-up
  3. Concierge / “Wizard of Oz” (manual service)
  4. Pre-sale, deposit or letter of intent
  5. Paid pilot

Interview rules

  • Ask about past behaviour, not future intentions.
  • Don't pitch; listen.
  • Interview payer and user separately.
  • PDPL: consent and minimum personal data.
Test card: We believe that [segment] will [behaviour]. We will test it by [experiment] and measure [metric]. We are right if [threshold] by [date]. If not, we will [pivot / stop / redesign]. Write the decision rule before the test.

Real cases — lessons learned

Zappos (1999): photographed shoes in local stores and bought each pair only after an online order. Desirability was proven before viability — test the money separately.
Dropbox (2007): a demo video before the full product; the waiting list reportedly jumped from about 5,000 to 75,000. Test the value with the cheapest artefact.
Quibi (2020): raised about USD 1.75 billion and shut down about six months after launch. Money does not replace evidence; reassess when the environment changes.
Abwaab (Jordan-founded edtech): research and focus groups first; usage later revealed demand for subjects the founders had not planned. Market wants cannot be assumed.
Session 4 · 14:45–15:10

MVP scope, prioritisation and resources

An MVP is the smallest thing that proves the riskiest assumption and reaches the first milestone. Everything else waits on a “Won't (this time)” list.

Backlog and user stories

  • Format: As a [user], I want [capability], so that [benefit].
  • Definition of done = evidence from a real user.
  • Non-software work: a simple WBS (deliverables → work packages).

Sizes and capacity

  • S ≤ 2 people-days · M 3–5 · L 6–10 · XL > 10 → split it.
  • Capacity = people × productive days per week × weeks. Plan ≤ 80%.

MoSCoW

MustWithout it the MVP fails or is illegal
ShouldImportant; a manual workaround exists
CouldNice to have if capacity remains
Won'tAgreed out of scope this time

Keep Musts at about 60% of effort or less (DSDM guideline).

Dependencies

Mandatory · discretionary · external · internal. Start external ones first — you cannot speed them up. Watch for scope creep and gold plating.

Real cases — lessons learned

Airbnb (2007): air mattresses in the founders' apartment and a simple website. The smallest MVP with a paying customer beats a full platform with none.
Instagram (2010): cut the Burbn app down to photos, filters and sharing. Usage data tells you what to cut.
Careem (2012): started with corporate car booking and manual dispatch; Uber agreed to acquire it for USD 3.1 billion in 2019. Start narrow, run it manually, then automate and expand.
Juicero (2016–2017): raised about USD 120 million for a connected juice press; the packs could be squeezed by hand. Gold plating is expensive; a Won't list protects money.
Session 5 · 15:10–15:40

Risk and founder accountability

An untested assumption is a risk. A risk without an owner is a surprise waiting to happen. A founding team without decision rights turns every surprise into a fight.

Write and score a risk

  • Because of [cause], [event] may happen, which would cause [effect].
  • Categories: market · technical · financial · legal/compliance · team.
  • Score = probability (1–5) × impact (1–5). Red ≥ 15 · amber 8–14 · green ≤ 7.
  • Each risk: one owner, a trigger (early sign) and an action.

Responses (PMI)

  • Threats: escalate · avoid · transfer · mitigate · accept.
  • Opportunities: escalate · exploit · share · enhance · accept.

Founder accountability

  • RACI: exactly one Accountable per milestone.
  • Decision rights: who decides product, technology, pricing, spending, hiring, equity; spending limits.
  • Deadlock rule: a time limit and an agreed tie-breaker.

Founders' agreement — minimum

  1. Roles and time commitment
  2. Equity and vesting
  3. IP assigned to the company
  4. Decision rights and deadlock rule
  5. What happens if a founder leaves

Register with the Companies Control Department and take legal advice.

Real cases — lessons learned

Airbnb (2020): raised about USD 2 billion, cut about 25% of roles and non-core businesses, then refocused. Speed comes from clear decision rights and a known runway.
Snapchat (2013–2014): a dispute with an early collaborator was settled for USD 157.5 million. Write the founders' agreement on day 1.
FTX (2022): the new CEO described “a complete failure of corporate controls”. Even a 3-person startup needs basic controls.
Theranos (2003–2018): technical problems were hidden instead of escalated; the founder was convicted in 2022. Bad news must travel fast.
Session 6 · 15:40–16:00

Agile operating rhythm

Plans don't execute themselves; rhythms do. A short, fixed weekly rhythm turns your A3, backlog and risk register into decisions every week.

Sprints or Kanban?

  • Sprints (1–2 weeks): building the product; fixed time, flexible scope; one sprint goal.
  • Kanban (continuous flow): operations, sales, support; limit work in progress.
  • Most startups use a hybrid: sprints for the product, Kanban for the rest.

Kanban board

Backlog → Ready (top 3) → Doing (WIP ≤ 2 per person) → Waiting (external) → Done. Fewer things in progress = faster finishing.

Decision log

Date · decision · options · who decided · why · review date. Stops re-arguing settled decisions.

Retrospective

What worked? What didn't? What one thing do we change for the next 2 weeks?

Weekly rhythm (Jordan work week: Sunday–Thursday)

MeetingWhenLengthOutput
Weekly planningSunday morning30 minTop 3 priorities, owners, WIP limits
Daily check-inEvery working day (or WhatsApp)10–15 minDone / doing / blocked
Weekly reviewThursday afternoon30–45 minKPIs, risk triggers, decisions
RetrospectiveEvery 2 weeks30 minOne improvement
Monthly re-planEnd of month60–90 minBudget vs. actual, runway, re-plan
OKR resetQuarterlyHalf a dayNew OKRs

Real cases — lessons learned

Toyota: Kanban comes from the Toyota Production System. Make work visible; limit what is in progress.
Amazon: a Weekly Business Review of controllable input metrics (Working Backwards, 2021). Review leading inputs weekly; outputs follow.
Basecamp: 6-week cycles and a 2-week cool-down (Shape Up, 2019). Fix the time, flex the scope.
Google: OKRs since 1999, set quarterly (Measure What Matters, 2018). An OKR without a weekly check-in is a wish.
Session 7 · 16:00–16:15

PMI tools and learning pathways

Apply first, then certify when it helps your role. Project skills are a career asset: PMI's Talent Gap report (2021) projected about 25 million new project professionals needed by 2030.
ResourceWhat it isAccess
PMI KICKOFF™Free course on project basics (agile or waterfall), templates, badge; about 45 minutesFree
PMI membershipPMI resources, standards and communityAnnual fee
PMI Infinity™PMI's AI assistant over PMI content, with sourcesFree for members
PMI Jordan ChapterAmman: development days, seminars, workshops, networking, volunteeringChapter membership
PMI Project Management Ready™Entry certification for school and university studentsVia Certiport
CAPM®Entry-level certificationExam fee reported USD 225 members / 300 non-members
PMI-CPMAI™Project management for AI products, data-firstCourse and certification
PMP®For experienced project leadersExperience required

CAPM facts

  • Eligibility: secondary degree + 23 hours of project management education before the exam; no work experience required.
  • Exam content (2023): fundamentals 36% · predictive 17% · agile 20% · business analysis 27%.
  • This workshop is not exam preparation and is not presented as counting toward the 23 hours.

Learning ladder

  1. This week: PMI KICKOFF (free).
  2. 30 days: run the weekly rhythm; attend one PMI Jordan Chapter event.
  3. 1–3 months: 23-hour course if CAPM is your goal; consider PMI membership.
  4. 3–6 months: CAPM exam (optional).
  5. Later: PMP; PMI-CPMAI for AI products.

Fees and formats change; check everything on pmi.org. Arabic content: see the PMI Jordan Chapter and its Edraak partner page.

Session 8 · 16:15–16:30

Closing: your next 30 days

You leave with a plan, a backlog, a risk register and a weekly rhythm. The value is in the next 30 days. Own the outcome, not the task.

Today's path

Diagnose (S1) → plan (S2) → test (S3) → scope (S4) → risks and roles (S5) → rhythm (S6) → keep learning (S7).

Your team outputs

Your 30-day commitment

Good: “Hold the first Thursday review on 5 November with 3 KPIs and the top-5 risk triggers — evidence: a decision-log entry.”
Weak: “Work on marketing” (no date, no evidence) · “Finish the app” (an output, not a 30-day step).

M.O.R.E. — the lens to keep

Thank you to the PMI Jordan Chapter, INJAZ mySTARTUP and the volunteers.

Templates · Word

Templates to reuse

Download the Word templates and use them with your team after the workshop. Each is available in English and Arabic.
TemplateSessionEnglishالعربية
Execution failure diagnostic handout (A4)1Downloadتنزيل
Diagnostic card (A5)1Downloadتنزيل
One-page execution plan (A3)2Downloadتنزيل
MVP backlog and prioritisation (A4)4Downloadتنزيل
Risk and assumption register (A3)3 and 5Downloadتنزيل
Weekly operating rhythm (A4)6Downloadتنزيل
PMI resources and learning pathway (A4)7Downloadتنزيل
30-day commitment cards (A6 ×4)8Downloadتنزيل

In the PDF version, download the templates from nxemtech-startup.nextmtech.com.

After the workshop · Take-home

Your 90-day budget, the PMI way

Turn your budget into a decision date: how much you need, what could go wrong, and when you must act.
  1. Estimate cost items per milestone — analogous (similar past item), parametric (rate × quantity), bottom-up (sum of details) or three-point: (optimistic + 4 × most likely + pessimistic) ÷ 6.
  2. Phase by month and add up the cost baseline.
  3. Add a contingency reserve for your top risks: probability × impact in JD (EMV).
  4. Add a management reserve (about 10%) for the unknown; use only with founders' approval.
  5. Check the funding limit: cash available ≥ budget? Runway = remaining cash ÷ net monthly burn.
  6. Write your decision date: “If [milestone] is not reached by [date], we fundraise or cut burn that week.”

Example (composite, Case A, JD)

LineAmount
Cost estimates for 90 days8,100
+ Contingency reserve (EMV of 2 risks)900
= Cost baseline9,000
+ Management reserve900
= Project budget9,900
Runway after day 90: (18,000 − 9,000) ÷ 3,0003 months

Monthly check (earned value, simplified)

Compare planned vs. actual spend and planned vs. actual progress. CPI = earned value ÷ actual cost; SPI = earned value ÷ planned value. Below 1.0 means act now.

Jordan reminders: 16% general sales tax on many purchases; Social Security once you hire; registration and licence renewals; an accountant for JoFotara-compliant invoicing.

Glossary and sources

Glossary (English → Arabic)

EnglishArabicEnglishArabic
Execution gapفجوة التنفيذProduct backlogقائمة عمل المنتج
Runway / Burn rateالمدى النقدي / معدل الإنفاقUser storyقصة المستخدم
Acceptance criteriaمعايير القبولDefinition of doneتعريف الإنجاز
Outcome / Outputالنتيجة / المُخرَجDependencyالاعتمادية
OKR (Objectives and Key Results)الأهداف والنتائج الرئيسيةScope creepزحف النطاق
MilestoneالمَعلمRisk registerسجل المخاطر
Leading / Lagging KPIمؤشر استباقي / لاحقTriggerمؤشر التفعيل
Assumption / Hypothesisالافتراض / الفرضيةRACIمصفوفة توزيع المسؤوليات
MVPالمنتج الأولي القابل للتطبيقDecision rightsصلاحيات القرار
Cost baselineخط أساس التكلفةContingency / Management reserveاحتياطي الطوارئ / احتياطي الإدارة

References